Hazardous areas
Royal Portbury Dock, Portishead, Bristol
At the end of November 2004, SR Electrical Services was approached via a consultant, to design and install the following electrical systems within a four week period, on behalf of Royal Portbury Docks on their newly formed dock berth 7.
The work included design and installation of:
• EExd certified flame proof lighting system.
• Automated fire water sprinkling system.
• Fire alarm system to BS – 5839-1: 2002.
• Automatic fuel offloading system utilising ‘Rotork’ valves.
This was achieved within the tight time scales by developing flexible working practices under very difficult weather conditions.
As a result of this project, SR Electrical Services continue to work with the Port Authorities and has completed work such as phase 2 pumping station designs and installation, wired automated system for 2 x no 3.3K.V. booster pump motors, including associated control panels and sub station work.
At the end of November 2004, SR Electrical Services was approached via a consultant, to design and install the following electrical systems within a four week period, on behalf of Royal Portbury Docks on their newly formed dock berth 7.
The work included design and installation of:
• EExd certified flame proof lighting system.
• Automated fire water sprinkling system.
• Fire alarm system to BS – 5839-1: 2002.
• Automatic fuel offloading system utilising ‘Rotork’ valves.
This was achieved within the tight time scales by developing flexible working practices under very difficult weather conditions.
As a result of this project, SR Electrical Services continue to work with the Port Authorities and has completed work such as phase 2 pumping station designs and installation, wired automated system for 2 x no 3.3K.V. booster pump motors, including associated control panels and sub station work.