Installation of additional “Clean Earth” underfloor busbar trunking and additional floor boxes.
- We have supplied and installed 2 Nº additional 3.6m lengths of ‘Electrak’.
- A new 3c10mm² XLPE/SWA/PVC cable has been installed from Distribution Board to the 2 Nº lengths of busbar trunking.
- The existing 6 Nº floor boxes under desk row Nº 4, 5 and 6 has now had 9m flexible conduit leads fitted and plugged into the new ‘Electrak’ underfloor busbar trunking.
- We have supplied and installed 1 Nº additional floor box complete with 2 Nº twin 13A sockets in each floor box at the end desk of each row of desk Nº 4, 5 and 6 to cope with the additional staff with the growth of their business.
Latest News
View all4 Signs Your Business is due a Hazardous Area Electrical Inspection
With the vast amount of directives and regulations surrounding hazardous areas, it can be easy to forget the importance of ensuring that the electrics within this area are safe.
Read more
Share
The Essentials of Electrical Control Panels and Why You Need One
You may be thinking, control panels, how would they benefit my business? Well, we can tell you that they are widely used in industrial, commercial, and residential applications and are essential for industrial automation.
Read more
Share
Latest Projects
View allHeader Point Lighting Rectification
Our team carried out a rectification project on faulty header point light fittings in Lerwick.
Additional Replacement Light Fitting
In December 2020, our team undertook rectification of a hazardous area light fitting in Northiam.