Installation of additional “Clean Earth” underfloor busbar trunking and additional floor boxes.

  • We have supplied and installed 2 Nº additional 3.6m lengths of ‘Electrak’.
  • A new 3c10mm² XLPE/SWA/PVC cable has been installed from Distribution Board to the 2 Nº lengths of busbar trunking.
  • The existing 6 Nº floor boxes under desk row Nº 4, 5 and 6 has now had 9m flexible conduit leads fitted and plugged into the new ‘Electrak’ underfloor busbar trunking.
  • We have supplied and installed 1 Nº additional floor box complete with 2 Nº twin 13A sockets in each floor box at the end desk of each row of desk Nº 4, 5 and 6 to cope with the additional staff with the growth of their business.

Latest News

View all

The Accreditations of a Good Electrical Contractor

June 2022

Certifications and qualifications serve as a good reflection of an electrical contractor’s experience and knowledge. A list of recognised accreditations should be on your list of criteria when looking to work with a potential new electrical contractor.

Read more Share Share on Twitter Share on LinkedIn

A Spotlight on Lighting Inspections

May 2022

Electrical safety should never be overlooked, especially in businesses and commercial properties that have hundreds of lights fitted.

Read more Share Share on Twitter Share on LinkedIn

Latest Projects

View all

Header Point Lighting Rectification

July 2021

Our team carried out a rectification project on faulty header point light fittings in Lerwick.

Read more

Additional Replacement Light Fitting

July 2021

In December 2020, our team undertook rectification of a hazardous area light fitting in Northiam.

Read more

ISO 14001 ISO 9001 CHAS APEA ECA CompEx NICEIC Approved Contractor NICEIC Hazardous Achilles Alcumus Safe Contractor